The Sundial Bridge at Turtle Bay crosses the Sacramento River in the heart of Redding, California. Opened July 4, 2004, the bridge links the north and south campuses of Turtle Bay Exploration Park and serves as a new downtown entrance for Redding’s extensive Sacramento River Trail system.

In addition to being a functional work of art, the Sundial Bridge is a technical marvel as well. The cable-stayed structure has an inclined, 217 foot pylon constructed of 580 tons of steel. The deck is made up of 200 tons of glass and granite and is supported by more than 4,300 feet of cable. The structure is stabilized by a steel truss, and rests on a foundation of more than 115 tons of steel and 1,900 cubic yards of concrete. The McConnell Foundation, a private, independent foundation established in Redding in 1964, funded the majority of the bridge’s $23 million cost.
World renowned Spanish architect and engineer Santiago Calatrava conceived the Sundial Bridge’s unusual design, his first free-standing bridge in the United States. Calatrava has built bridges, airports, rail terminals, stadiums, and other structures around the world. His notable designs include the new PATH transportation terminal at the World Trade Center site in New York City and several projects at the 2004 Olympic Games in Athens, Greece, including the main stadium where opening and closing ceremonies were held.
STATISTICS
Completion And Opening July 4, 2004
Dimensions
- 700 feet long
- 23 feet wide
- 217 feet high (pylon)
Weight
- 3.2 million pounds (1,600 tons)
Materials
- steel structure with galvanized steel cables
Deck Materials
- non-skid glass panels in steel framework, granite accents
Foundation
- 115 tons of rebar
- 1,900 cubic yards of concrete
Superstructure
- 400 tons of steel
- 200 tons of glass and granite for the deck Cables
- 4,342 feet of cable, Pylon
- 580 tons of steel
Funding
Funders
- The McConnell Foundation
- Redding Redevelopment Agency
- Federal Highway Administration
- Turtle Bay Exploration Park
Project Team
Architect
- Santiago Calatrava (Zurich)
Construction Manager
- Bob Morrison Jr., S.E./Morrison Structures, Inc. (Redding, CA)
Inspection
- Omni Means (Redding/Roseville, Calif.)
Project Manager
- Margaret Zech
General Contractor
- Kiewit Pacific Co. (Vancouver, Wash.)
Steel Fabricator
- Universal Structural, Inc. (Vancouver, Wash.)
Steel Detailers
- Tensor Engineering
Erection Engineers
- Buckland and Taylor
Other Consultants and Contractors
- Sharrah Dunlap Sawyer, Stimpel-Wiebelhaus, Northstate Resources, Carr Kennedy Peterson Frost, Coyote & Fox, Pace Engineering, Shasta Water Action Group, L.T. Mlcoch, Inc., and others.
Helpful Comparisons
Concrete
The amount of concrete used in the bridge foundation (1,900 cubic yards) is equivalent to the amount needed to complete foundations for 43 homes. It took 6.27 million cubic yards of concrete to make Shasta Dam and 16,000 cubic yards for the base of the TransAmerica Tower.
Weight
The Space Needle weighs 3,700 tons — more than twice as much as the 1,600-ton Calatrava Bridge. The Eiffel Tower weighs 7,000 tons and the Golden Gate Bridge is 419,800 tons.
Cables
The superstructure will be made of enough cable to stretch across more than 14 football fields.
Pre-fabrication
Due to the sensitivity of the riparian site, steel for the bridge is being pre-fabricated at USI, a steel yard in Vancouver, Washington. A total of 18, 40-foot deck sections and 25 truck loads of pylon pieces were transported from Vancouver to Turtle Bay. Fourteen large pieces were shipped by barge to Vallejo and then trucked to Redding, sometimes taking up the entire freeway. The trucks will travel at night and during the weekends to avoid significant traffic delays. The effort requires the coordination of three state Highway Patrol agencies.
No comments:
Post a Comment